Customers must ensure they have sufficient PowerHA SystemMirror for i entitlements as specified in the product license terms. Refer to the software license agreement:
...
Expand | ||
---|---|---|
| ||
When upgrading from a prior release, if 5770HAS option 1 is not installed, the manual installation of 5770HAS Option 1 is required either before or after the upgrade. Since PowerHA 7.5 has a new product structure (including new SWMA PIDs), this requires an upgrade in e-config rather than in IBM Entitled System Support (ESS). The following behavior applies to upgrades:
|
...
PowerHA 7.2 and 7.4 contain three editions. The product verifies compliance against all installed options. Therefore, only install entitled options to ensure that no out-of-compliance messages are issued. For example, if a system is entitled to PowerHA SystemMirror for i Standard Edition, only the following options should be installed: PowerHA SystemMirror for i (*BASE) and PowerHA for i Standard Edition (Option 2).
Tip |
---|
Enterprise Edition Upgrade PowerHA enterprise edition is an upgrade on top of PowerHA standard edition and requires a license and active SWMA for both PowerHA System Mirror for i standard edition and PowerHA SystemMirror for i enterprise edition. |
...
In the event PowerHA is using more processors than the usage limit, a new 70-day grace period will begin. While running outside of compliance during this grace period, PowerHA will continue working. This will allow uninterrupted HA operations while working to acquire the proper entitlements and keys. After the 70-day grace period, either reduce the number of processors being used by PowerHA or obtain the proper entitlement and install your new license keys in order to continue to function.
Tip |
---|
IBM Power Systems Capacity BackUp (CBU) Offering The IBM Power Systems Capacity BackUp offering provides flexible and economical options for secondary systems in a PowerHA environment. When utilizing the CBU offering, temporary keys enable uninterrupted PowerHA functionality on CBU systems by providing keys with the same usage limit entitlements as the production system. For additional information see IBM Power Systems: Capacity BackUp |
...